a team meeting was held to put the project into perspective. we made a record of what we have completed and what we still have to do at this point.
completed work
•Scenes
•1 Ethan, almost done, sound needed
•2 Jack, not much done but getting there.
•3 Martin almost done, sound needed
•4 Ethan almost done, sound needed
•5 Nat credits
•6 Nat, Jack and Martin
remaining work
•Ethan – finish environments, creatures for scene 4, texture characters and creatures properly, sounds for scenes and editing. Finish by end of week holiday.
•Martin – finish farm surroundings, change certain part of 3D village, sounds for scene and editing. Finish by end of week holiday.
•Jack – learn to animate creature and scene 3, and video editing for scene 2. last scene animation. Finish by end of week holiday.
•Nat – credits, final editing, sounds, last scene camera work. Finish by end of week holiday.